100' x 100' Steel Hangar & Door has been ordered. Deposit has been paid and we are expecting a Spring 2021 delivery!
Longterm Ground lease, Development Agreement, and Site Plan have been signed and approved!
Asphalt on the building site has been removed.
Re-route of the storm sewer is in progress.
With the generous support of the Community and Stearman Friends, we have received or obtained pledges to cover the initial cost of the hangar and erection of the Stearman Community Center! We still need your help for completion of the project. The final completion of the hangar will include space for the "Stearman Office", retail area, seminar and banquet space, repository for artifacts and related memorabilia, additional offices for Stearman-related organizations, storage areas, and full men and women's restrooms.