Progress Report November 2020

Building

Bids have been obtained for a 100' x 100' steel building.

Longterm Ground Lease has been signed by the City of Galesburg & Stearman Foundation.

Site Plan is in progress.

Timeline

Order the building - Fall 2020

Site work - Spring 2021

Construction - Summer 2021

Funding

Stearman Foundation has committed $250,000 to the building project.

Stearman Foundation / Fly-In Board members have pledged an additional $100,000.

City of Galesburg is on target for site work contributions over $150,000.

Goal

Construction of the steel building and, ultimately, the offices will cost approximately $750,000.

The goal is to have the building completed by the next year's 50th National Stearman Fly-In.

After the 50th National Stearman Fly-In, work will begin on the office layout.